Status of Pipeline and Booster Pump Project

The transmission line is installed.  Fire hydrants have been connected to the new line which will remain active all winter. All road crossings have been paved and the trench along the roadways has been repaired.  Construction on the booster pump station will take place as soon as possible in the spring. LPC would like to thank all of the residents for their patience in dealing with any inconvenience this construction may have caused.